Contract for modernization of line 1

18/09/2015

Following modernization in spring 2015 of the combustion system in line 2 of the Hennepin plant, we also received an order on 24/08/2015 to modernize the combustion system in line 1 of the same plant. This will take place in 2016. Our scope of supply comprises the supply and erection supervision activities for the main components of the feeder, horizontal grate, grate siftings discharge and hydraulic systems.

The Hennepin plant was started up in 1989 and comprises 2 combustion lines, each equipped with the MARTIN horizontal grate and designed for a throughput of 552 t/day.